Kensington Dr. (Eastern Section)

​Scope


  • This project is intended to improve vehicular mobility and reduce congestion on Kensington Drive between Connell's Point Drive and Providence Road by permanently removing the existing on-street parking spaces and replacing them with vehicular travel lanes. 

​Project Status


  • State funding approved mid 2018. Environmental Document was approved by the State. Additional funding from CRTPO for utility relocation costs has been approved. Next phase is to engage Right-of-Way acquisition.

​Estimated Schedule


  • Design Phase: 1st Quarter 2017-3rd Quarter 2018 (85% Plans Completed)
  • Right-of-way Acquisition and Utility Relocation Phase: 2nd Quarter 2020 - 1st Quarter 2021
  • Bid Phase: 2nd Quarter 2021
  • Construction Phase: 2nd Quarter 2021-4th Quarter 2021

Next Steps


  • Plans to be finalized, Right-of-Way acquired, utilities to be relocated, project bid and constructed.
Kensington Drive Eastern Section