Gray Byrum & NC 16 Intersection

​Scope


  • NCDOT will be constructing a north bound left turn lane and southbound right turn lane on NCDOT as part of their SPOT Safety Project.  The Town will fund a traffic signal as part of the project.   

Estimated Schedule

  • Design Phase: 2nd Quarter 2018 - 4th Quarter 2018
  • Right-of-way Acquisition Phase: 4th Quarter 2018 - 1st Quarter 2019
  • Construction Phase: 3rd Quarter 2019 - 4th Quarter 2019

Next Steps


  • Design efforts are underway.