Gray Byrum & NC 16 Intersection

​Scope


  • NCDOT will be constructing a north bound left turn lane and southbound right turn lane on NCDOT as part of their High Hazard Safety Project.  The Town will fund a traffic signal as part of the project.   

Estimated Schedule

  • Design Phase: 2nd Quarter 2020 - 4th Quarter 2020
  • Right-of-way Acquisition & Utility Relocation: Complete
  • Construction Phase: 2nd Quarter 2021 - 4th Quarter 2021 Construction date TBD