NC-75 & Old Providence Road (U-6248)

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project Highlights

Responsible Party: North Carolina Department of Transportation (NCDOT) with Town of Waxhaw contribution

Estimated Completion Date: 2030

Project Details:

  • Construct a roundabout at the intersection of NC-75 & Old Providence Road
  • Projected schedule: 
    • July 2025 - Right-of-way acquisition 
    • July 2026 - Utilities relocation 
    • May 2027/28 - Award construction contract

NC-75 & Old Providence Road Roundabout Project Map

Please note: The information provided on this page is intended as a general overview of the project and its anticipated timeline. Project schedules are subject to change based on weather, contractor availability, utility conflicts, and other unforeseen circumstances. Dates and details are not guaranteed and may be updated as new information becomes available.