New Town Road & Cuthbertson Road (HL-0135)

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project Highlights

Responsible Party: North Carolina Department of Transportation (NCDOT) with Union County and Village of Wesley Chapel involvement

Estimated Completion Date: 2029

Project Details:

  • Construct a roundabout at the intersection of New Town Road & Cuthbertson Road
  • Projected schedule:
    • Nov. 2025 - Right-of-way acquisition
    • Nov. 2026 - Utilities relocation
    • Jan. 2028 - Award construction contract

New Town Road & Cuthbertson Road Roundabout Project Map

Please note: The information provided on this page is intended as a general overview of the project and its anticipated timeline. Project schedules are subject to change based on weather, contractor availability, utility conflicts, and other unforeseen circumstances. Dates and details are not guaranteed and may be updated as new information becomes available.