Project Highlights
Responsible Party: North Carolina Department of Transportation (NCDOT) with Union County and Village of Wesley Chapel involvement
Estimated Completion Date: 2029
Project Details:
- Construct a roundabout at the intersection of New Town Road & Cuthbertson Road
- Projected schedule:
- Nov. 2025 - Right-of-way acquisition
- Nov. 2026 - Utilities relocation
- Jan. 2028 - Award construction contract
Please note: The information provided on this page is intended as a general overview of the project and its anticipated timeline. Project schedules are subject to change based on weather, contractor availability, utility conflicts, and other unforeseen circumstances. Dates and details are not guaranteed and may be updated as new information becomes available.